The integration of constrained resources into top-down project control

Martens, Annelies
Vanhoucke, Mario
Citations
Altmetric:
Publication Type
Journal article with impact factor
Editor
Supervisor
Publication Year
2017
Journal
Computers & Industrial Engineering
Book
Publication Volume
110
Publication Issue
Aug
Publication Begin page
277
Publication End page
288
Publication Number of pages
Collections
Abstract
The timely completion of a project is one of its main factors for success. During the scheduling phase, a project buffer can be installed to protect the project deadline. During the execution phase, tolerance limits that generate warning signals when the project deadline is endangered should be constructed to monitor the buffer consumption. These tolerance limits will be constructed for the dynamic progress data provided by the Earned Value Management/Earned schedule methodology (EVM/ES). In this paper, we incorporate information on the availability of scarce resources into the construction of analytical tolerance limits for EVM/ES, in order to improve the efficiency and reliability of these tolerance limits. In order to review the performance of the limits, a computational experiment has been carried out in which they are compared to analytical tolerance limits that disregard the availability of resources. Results have shown that the performance of analytical tolerance limits can be significantly enhanced by incorporating the available resource information.
Research Projects
Organizational Units
Journal Issue
Keywords
Mathematical Models, Mathematical Models of Scheduling, Deadlines, Scarcity, Project Management, Tolerance Intervals (Statistics)