Progress payments in project scheduling problems

Vanhoucke, Mario
Demeulemeester, Erik
Herroelen, Willy
Citations
Altmetric:
Publication Type
Journal article with impact factor
Editor
Supervisor
Publication Year
2003-08
Journal
European Journal of Operational Research
Book
Publication Volume
148
Publication Issue
3
Publication Begin page
604
Publication End page
620
Publication Number of pages
Collections
Abstract
In this paper we study the unconstrained project scheduling problem with discounted cash flows where the net cash flows are assumed to be dependent on the completion times of the corresponding activities. Cash outflows occur when an activity is completed whereas cash inflows are incurred as progress payments at the end of some time period. The objective is to schedule the activities in order to maximize the net present value of the project subject to the precedence constraints and a fixed deadline. This paper extends the ever-growing amount of research concerning the financial aspects in project scheduling in which cash flows are time-dependent.We introduce a branch-and-bound algorithm which computes upper bounds by making piecewise linear overestimations. In doing so, the algorithm transforms the problem into a weighted earliness–tardiness project scheduling problem. The algorithm is extended with two new rules in order to reduce the size of the branch-and-bound tree. Computational results are reported.
Research Projects
Organizational Units
Journal Issue
Keywords
4901 Applied Mathematics, 40 Engineering, 49 Mathematical Sciences
Citation
Knowledge Domain/Industry
Embedded videos