The impact of various activity assumptions on the lead-time and resource utilization of resource-constrained projects

Debels, Dieter
Vanhoucke, Mario
Citations
Altmetric:
Publication Type
Working paper
Editor
Supervisor
Publication Year
2006
Journal
Book
Publication Volume
Publication Issue
15
Publication Begin page
Publication End page
Publication NUmber of pages
31
Collections
Abstract
The well-known resource-constrained project scheduling problem (RCPSP) schedules project activities within the precedence and renewable resource constraints while minimizing the total lead-time of the project. The basic problem description assumes non-pre-emptive activities with fixed durations, and has been extended to various other assumptions in literature. In this paper, we investigate the effect of three activity assumptions on the total lead-time and the total resource utilization of a project. More precisely, we investigate the influence of variable activity durations under a fixed work content, the possibility of allowing activity pre-emption and the use of fast tracking to decrease a project's duration. We give an overview of the procedures developed in literature and present some modifications to existing solution approaches to cope with our activity assumptions under study. We present computational results on a generated dataset and evaluate the impact of all assumptions on the quality of the schedule.
Research Projects
Organizational Units
Journal Issue
Keywords
Programme & Portfolio Management
Citation
Knowledge Domain/Industry
DOI
Other links
Embedded videos