A study of the critical chain project management method applied to a multiproject system

Eduardo Cooper Ordoñez, Robert
Vanhoucke, Mario
Coelho, José
Novaski, Olívio
Citations
Altmetric:
Publication Type
Journal article with impact factor
Editor
Supervisor
Publication Year
2019
Journal
Project Management Journal
Book
Publication Volume
50
Publication Issue
3
Publication Begin page
322
Publication End page
334
Publication Number of pages
Collections
Abstract
In 1997, Eliyahu Goldratt proposed a method called critical chain project management (CCPM) to minimize the inefficiencies identified in traditional project management. The project management community accepted the proposed method as a viable alternative. However, to allow its implementation with a multiproject system, more research was necessary. Seeking to identify the key factors that influence the performance of the multiproject system applying the CCPM method, we performed a case study. Logistic regression analysis showed that applying the CCPM method in a multiproject system allows for better time estimation of activities and facilitates the allocation of critical resources.
Research Projects
Organizational Units
Journal Issue
Keywords
Project Scheduling, Critical Chain Method, Multiproject Management, Resource Allocation, Logistic Regression Analysis