dc.contributor.authorDebels, Dieter
dc.contributor.authorVanhoucke, Mario
dc.date.accessioned2017-12-02T14:23:32Z
dc.date.available2017-12-02T14:23:32Z
dc.date.issued2006
dc.identifier.urihttp://hdl.handle.net/20.500.12127/1987
dc.description.abstractResource-constrained project scheduling with activity pre-emption assumes that activities are allowed to be interrupted and restarted later in the schedule at no extra cost. In the current paper, we extend this pre-emptive scheduling problem with setup times between activity interruptions and the possibility to fast track pre-emptive subparts of activities. The contribution of the paper is twofold. First, we present an optimal branch-and-bound procedure for the pre-emptive resource-constrained project scheduling problem with setup times and fast tracking options. Second, we test the impact of these pre-emptive extensions to the quality of the schedule from a lead-time point-of-view.
dc.language.isoen
dc.subjectProgramme & Portfolio Management
dc.titlePre-emptive resource-constrained project scheduling with setup times
refterms.dateFOA2019-10-14T14:27:09Z
dc.source.issue19
dc.source.numberofpages37
vlerick.knowledgedomainOperations & Supply Chain Management
vlerick.supervisor
vlerick.typecommWorking paper
vlerick.vlerickdepartmentTOM
dc.relation.urlhttp://public.vlerick.com/Publications/4c642c0d-6aa9-e011-8a89-005056a635ed.pdf
dc.identifier.vperid117045
dc.identifier.vperid58614
dc.identifier.vpubid2224