Discrete time/cost trade-offs in project scheduling with time-switch constraints

Vanhoucke, Mario
Demeulemeester, Erik
Herroelen, Willy
Citations
Altmetric:
Publication Type
Journal article with impact factor
Editor
Supervisor
Publication Year
2002
Journal
Journal of the Operational Research Society
Book
Publication Volume
53
Publication Issue
7
Publication Begin page
741
Publication End page
751
Publication NUmber of pages
Collections
Abstract
The discrete time/cost trade-off problem assumes the duration of project activities to be discrete, non-increasing functions of the amount of a single non-renewable resource. The problem has been studied under three possible objectives. The so-called deadline problem involves the scheduling of project activities in order to minimize the total cost of the project while meeting a given deadline. The budget problem aims at minimizing the project duration without exceeding a given budget. A third objective involves the generation of the complete efficient time/cost profile over the set of feasible project durations. In this paper we describe a solution procedure for the deadline problem in which three special cases of time-switch constraints are involved.